In time and work we will learn to calculate and find the time required to complete a piece of work and also find work done in a given period of time. We know the amount of work done by a person varies directly with the time taken by him to complete the work.
(i) Suppose A can finish a piece of work in 8 days.
Then, work done by A in 1 day = ¹/₈ [by unitary method].
(ii) Suppose that the work done by A in 1 day is ¹/₆
Then, time taken by A to finish the whole work = 6 days.
(i) Suppose if a person A can finish a work in n days.
Then, work done by A in 1 day = 1/nᵗʰ part of the work.
(ii) Suppose that the work done by A in 1 day is \(\frac{1}{n}\)
Then, time taken by A to finish the whole work = n days.
Solution:
Time taken by Aaron to finish the work = 12 days.
Work done by Aaron in 1 day = ¹/₁₂
Time taken by Brandon to finish the work = 15 days.
Work done by Brandon in 1 day = ¹/₁₅
Work done by (Aaron + Brandon) in 1 day = ¹/₁₂ + ¹/₁₅ = ⁹/₆₀ = ³/₂₀
Time taken by (Aaron + Brandon) to finish the work = \(\frac{20}{6}\) days, i.e., 6²/₃ days.
Hence both can finish the work in 6²/₃ days.
Solution:
Time taken by (A + B) to finish the work = 15 days.
Time taken by B alone to finish the work 20 days.
(A + B)’s 1 day’s work = ¹/₁₅
and B’s 1 day’s work = ¹/₂₀
A’s 1 day’s work = {(A + B)’s 1 day’s work} - {B’s 1 day’s work}
= (¹/₁₅ - ¹/₂₀) = (4 - 3)/60 = ¹/₆₀
Therefore, A alone can finish the work in 60 days.
Solution:
Time taken by A to finish the work = 25 days.
A’s 1 day’s work = ¹/₂₅
Time taken by B to finish the work = 20 days.
B’s 1 day’s work = ¹/₂₀
(A + B)’s 1 day’s work = (¹/₂₅ + ¹/₂₀) = ⁹/₁₀₀
(A + B)’s 5 day’s work (5 × ⁹/₁₀₀) = 4̶5̶/1̶0̶0̶ = ⁹/₂₀
Remaining work (1 - ⁹/₂₀) = ¹¹/₂₀
Now, ¹¹/₂₀ work is done by B in 1 day
Therefore, ¹¹/₂₀ work will be done by B in (11/2̶0̶ × 2̶0̶) days = 11 days.
Hence, the remaining work is done by B in 11 days.
Solution:
Time taken by (A + B) to finish the work = 18 days.
(A + B)’s 1 day’s work = ¹/₁₈
Time taken by (B + C) to finish the work = 24 days.
(B + C)’s 1 day’s work = ¹/₂₄
Time taken by (C + A) to finish the work = 36 days.
(C + A)’s 1 day’s work = ¹/₃₆
Therefore, 2(A + B + C)’s 1 day’s work = (¹/₁₈ + ¹/₂₄ + ¹/₃₆) = (4 + 3 + 2)/72 = \(\frac{9}{72}\) = ¹/₈
⇒ (A + B + C)’s 1 day’s work = (¹/₂ × ¹/₈) = ¹/₁₆
Therefore, A, B, C together can finish the work in 16 days.
Solution:
Time taken by (A + B) to finish the work = 12 days.
(A + B)’s 1 day’s work = ¹/₁₂
Time taken by (B +C) to finish the work = 15 days.
(B + C)’s 1 day’s work = ¹/₁₅
Time taken by (C + A) to finish the work = 20 days.
(C + A)’s 1 day’s work = ¹/₂₀
Therefore, 2(A + B + C)’s 1 day’s work = (¹/₁₂ + ¹/₁₅ + ¹/₂₀) = \(\frac{12}{60}\) = ¹/₅
⇒ (A + B + C)’s 1 day’s work = (¹/₂ × ¹/₅) = ¹/₁₀
Therefore, A, B, C together can finish the work in 10 days.
Now, A’s 1 day’s work
= {(A + B + C)’s 1 day’s work} - {(B + C)’s 1 day’s work}
= (¹/₁₀ - ¹/₁₅) = ¹/₃₀
Hence, A alone can finish the work in 30 days.
B’s 1 day’s work
{(A + B + C)’s 1 day’s work} - {(C + A)’s 1 day’s work}
(¹/₁₀ – ¹/₂₀) = ¹/₂₀
Hence, B alone can finish the work in 20 days.
C’s 1 days work
= {(A + B + C)’s 1 day’s work} - {(A + B)’s 1 day’s work}
= (¹/₁₀ – ¹/₁₂) = ¹/₆₀
Hence, C alone can finish the work in 60 days.
● Time and Work
Practice Test on Time and Work
● Time and Work - Worksheets
8th Grade Math Practice
From Time and Work to HOME PAGE
Didn't find what you were looking for? Or want to know more information about Math Only Math. Use this Google Search to find what you need.
Nov 22, 24 01:00 AM
Nov 22, 24 12:34 AM
Nov 22, 24 12:12 AM
Nov 20, 24 12:50 AM
Nov 20, 24 12:16 AM
New! Comments
Have your say about what you just read! Leave me a comment in the box below. Ask a Question or Answer a Question.